Smith Brothers starts work on energy storage site
Work has started on the first of Arlington Energy's energy storage and gas peaking projects - a short term operating reserve (STOR) site - that will provide back-up power generation to National Grid.
11th April 2019 by Networks

High voltage power contractor Smith Brothers is working on the project, which is based in Sheffield, Yorkshire.
With work having commenced on the Chesterfield Road development earlier this month, the site is set to house eight gas generators and the associated infrastructure. Once complete, the plant will provide back-up power generation to National Grid. Smith Brothers is also working alongside Northern Power Grid (NPg) to achieve a 66kV connection for the power generation of the plant.
The planned turnkey programme of works will see the contractor carry out all engineering, procurement and construction (EPC) civil and electrical engineering aspects of the connection assignment – from initial design, through to final commissioning.
Dave Ogden, director at Smith Brothers, said: “We’re delighted that work has commenced on Sheffield’s Chesterfield Road gas-peaking project. This is the first STOR site set to be added to Arlington Energy’s planned 1GW portfolio of UK energy storage and gas peaking projects, and we’re proud to be working alongside such a renowned brand.
“We have worked closely with Arlington to move the portfolio forward over the past year, and we are delighted that our technical expertise enables us to support them during this significant new phase of growth.”
The EPC works will include the procurement, delivery, installation and commissioning of eight 2.5MW gas generators and an 11kV switchboard – as well as the required on-site gas pipe engineering. Meanwhile, private works will include planning, proving and laying of the cable route, as well as procurement, delivery, installation and commissioning of a 66/11kV power transformer and 66kV switchgear – alongside all associated infrastructure.
Matt Clare, director of Arlington Infrastructure added: “It’s great to see work having started on the Chesterfield Road site. It’s the first of many gas peaking projects Arlington has in the pipeline and given the scale of our portfolio and approach to the market generally, it was crucial that we partnered with a trusted counterparty who would take care of all our EPC and technical needs.”
The Smith Brothers team, along with a project manager, site manager and several sub-contractors, will work towards the final commissioning of the scheme – and subsequent energisation – by September 2019.
Comments
Login on register to comment
Related content

Gas
Cadent backs launch of major bio-CNG HGV refuelling station
Gas network’s £250,000 infrastructure investment ensures supplies to existing connected customers have not been impacted

Gas
Editor’s blog: The biggest tests of resilience are yet to come
Network content director Jane Gray reflects on the industry's coronavirus response to date and the challenges still to come.

Gas
From the front line: Chris Garside and Andy Simcoe, Northern Gas Networks
Key workers across the power and gas networks are playing a critical role in the national response to Coronavirus. Network has committed to profiling their stories.
Related supplier content

Power
Load patterns and lockdown: how Covid-19 is impacting electricity networks
Insights into dynamics on the low voltage network as the outbreak unfolds

Downloads
Protect electrical equipment from insulation failure
Insulation faults are a major cause leading to the eventual failure of electrical equipment. Partial discharge (PD) is a very reliable indicator of developing insulation faults. Regular PD testing allows users to detect and analyze PD activity

Heat
How E.ON. is helping the City of London become a zero emissions city
Discover Citigen. Deep in the heart of our bustling capital