SSEN substation reinforcement approved by Highland Council

Scottish and Southern Electricity Networks (SSEN) has secured planning consent for the upgrade and refurbishment of its transmission substation at Fort Augustus.

1st November 2018 by Networks

SSEN substation reinforcement approved by Highland Council

Highland Council gave planning approval at a special meeting on 23 October. The project is required to connect new electricity generation projects but will also help to support increased security of supply in the local area. The main elements of the project comprise of:

  • Expansion of the existing substation footprint
  • Construction of three new buildings that will house electrical switchgear
  • The construction and connection of four new transformers and reactor units
  • Construction of new, overhead aluminium structures (busbars) and underground connections within the expanded substation footprint
  • The relocation and removal of existing substation equipment.

SSEN’s lead project manager, Archie Munro, said: “We welcome Highland Council’s planning approval for the Fort Augustus Substation Reinforcement project, enabling the connection of further renewables’ development in the Scottish Highlands whilst also strengthening security of supply for the rural communities we serve.

“We would particularly like to thank the local community and wider stakeholders that have consulted with us and provided feedback throughout the development process and as we worked to refine the final planning submission. Main contract works for the substation works are expected to commence in early Spring 2018 following discharge of our planning conditions, and we look forward to ongoing engagement with our host communities as plans for construction progress.”