WPD completes Nottinghamshire network improvements
Western Power Distribution has completed a four-year scheme to reinforce the electricity network in East Leake and Stanford on Soar in Nottinghamshire.
28th June 2018 by Networks

The work, which has been carried out by WPD’s Keyworth team, has enabled the former Stanford Hall site to be redeveloped. The site is currently undergoing a £300 million transformation and is due to reopen later this year as the country’s new military Defence and National Rehabilitation Centre (DNRC), replacing Headley Court in Surrey.
To enable the redevelopment to take place, the team first had to install a temporary 800kVA substation so supplies to the site could be transferred to allow the existing substation to be demolished. They also had to arrange for around 1km of 11kV cables on the site to be diverted to make way for the new 47,000m2 state-of-the-art facilities.
Extensive reinforcement work to WPD’s existing network was also carried out.
Team manager Steve Hayward said: “This has involved rebuilding a 4.5km mixed overhead and underground circuit and overlaying a 5km underground circuit from the local primary substation. We have also installed more modern equipment at the substations along the route which will help to further improve supply reliability to around 1,000 properties in East Leake and Stanford on Soar, and better accommodate any increased demands placed on the power network in the future.
“In addition to this we have changed three secondary substations along the route, which were earmarked for change in ED1.”
Construction work began on the MOD site in early 2015 and WPD’s new 3MVA substation was commissioned in June 2017, enabling the temporary one to be removed in early 2018.
“Despite the magnitude of construction work that has been ongoing on the site and the huge number of different contractors involved, we have been able to successfully deliver the electrical connection on schedule and on budget which is a credit to the Keyworth team,” added Hayward.
Comments
Login on register to comment
Related content

Power
The future for vegetation management
Why networks should focus on data not trees to overcome the costly challenges involved in vegetation management

Power
An unprecedented opportunity for change
Why short interruptions will matter in RIIO-ED2 and how to address them.

Power
Time for less talk and more action on decarbonisation
Core "oven-ready" solutions to decarbonising heat and transport exist today and should be implemented without delay, says WPD's future power networks expert.
Related supplier content

Power
Load patterns and lockdown: how Covid-19 is impacting electricity networks
Insights into dynamics on the low voltage network as the outbreak unfolds

Downloads
Protect electrical equipment from insulation failure
Insulation faults are a major cause leading to the eventual failure of electrical equipment. Partial discharge (PD) is a very reliable indicator of developing insulation faults. Regular PD testing allows users to detect and analyze PD activity

Heat
How E.ON. is helping the City of London become a zero emissions city
Discover Citigen. Deep in the heart of our bustling capital