SSEN and Piclo to deliver ‘proactive flexibility’
Businesses, households and communities based in Scottish and Southern Electricity Networks' (SSEN) distribution regions could be paid for the provision of flexibility services.
27th March 2019 by Networks

SSEN has announced an agrement with Piclo, the independent marketplace for buying and selling smart grid flexibility services, and is extending the opportunity for flexibility beyond Constraint Managed Zones (CMZ), to providers across its entire network.
These services could range from small-scale renewables, battery storage, electric vehicles, demand side response and even energy efficiency measures that alleviate network constraint.
Traditionally increased demand would be facilitated through network reinforcement. However, since 2015 SSEN has sought to manage this increased pressure through supporting flexibility technologies to alleviate constraints on the network, through CMZ.
SSEN and Piclo are now calling upon all existing, potential and interested flexibility providers to register at Piclo now, and be an active part in delivering a smarter, flexible and more cost-effective network.
Payment for providing flexibility services will commonly consist of an availability payment and a utilisation payment, and typically be around £300/MWh. Providers will also benefit from a new streamlined approach to the procurement, auction, contracting and settlement processes that Piclo provides.
Stewart Reid, head of future networks at SSEN, said: “I am delighted that SSEN and Piclo are taking this significant step forward in delivering Proactive Flexibility, which could play an important role in supporting the UK transitioning to a low-carbon economy.
“SSEN is committed to being a neutral facilitator of local and national markets that are created by the transition to a flexible network. To do this successfully visibility, transparency and accessibility will be key. Too often asset owners that may be considering providing flexibility services find that the process is neither clear nor simple.
“With Piclo we are hoping to address that challenge, to provide the communities in which we operate a level-playing field that supports local solutions and builds a network of flexibility providers.”
James Johnston, CEO and co-founder at Piclo, said: “Today’s deal with SSEN is really important for Piclo following our successful UK-wide pilot. We’re delighted to be partnering with SSEN to strengthen its flexibility ambitions.
“Piclo was founded in response to the growing problems posed by UK electricity grid congestion which is restricting growth of low-carbon power, causing significant costs to consumers. Whilst some physical changes to the network will be required as we decarbonise, Piclo’s platform significantly reduces the need for new investment, minimising the cost to the consumer whilst maximising the role of flexible, low-carbon plant in the overall mix.
Initially SSEN will procure flexibility through four services:
CMZ Prevent – the traditional CMZ product that supports the management of peak demand.
CMZ Prepare – which will support the network during planned maintenance work.
CMZ Respond – designed to support the network during fault conditions as a result of maintenance work
CMZ Restore – to support the network during faults that occur as a result of equipment failure.
SSEN is in the process of developing a further three additional CMZ service types with the expectation these will be released in late 2019.
Comments
Login on register to comment
Related content

Power
The future for vegetation management
Why networks should focus on data not trees to overcome the costly challenges involved in vegetation management

Power
An unprecedented opportunity for change
Why short interruptions will matter in RIIO-ED2 and how to address them.

Power
Time for less talk and more action on decarbonisation
Core "oven-ready" solutions to decarbonising heat and transport exist today and should be implemented without delay, says WPD's future power networks expert.
Related supplier content

Power
Load patterns and lockdown: how Covid-19 is impacting electricity networks
Insights into dynamics on the low voltage network as the outbreak unfolds

Downloads
Protect electrical equipment from insulation failure
Insulation faults are a major cause leading to the eventual failure of electrical equipment. Partial discharge (PD) is a very reliable indicator of developing insulation faults. Regular PD testing allows users to detect and analyze PD activity

Heat
How E.ON. is helping the City of London become a zero emissions city
Discover Citigen. Deep in the heart of our bustling capital