Power Networks Demonstration Centre: tried and tested technology
Network visited the Power Networks Demonstration Centre to find out about recent technologies to pass through its accelerated testing regimes.
11th March 2016 by Networks

[image_library_tag b01d9d8a-d981-4f32-8e0a-5acbe0a8b3bc 150×150 alt=” main building” width=”150″ border=”0″ ]PNDC HQ PNDC main building
The Power Networks Demonstrations Centre (PNDC), located near Glasgow, is a not for profit facility which aims to accelerate time to market for new power network technologies. It does this through a process of intensive failure testing on its unique private network. The centre has been open almost two years and here we profile some key technologies to pass muster and make the leap to real network application:
1) Hybrid generator – diesel engine & battery storage
PNDC trialled two hybrid generator technologies from two technology developers both of which combined a diesel engine + alternator with a battery pack. The batteries were based on different chemistries however (one was a 300 kVA unit based on sealed gel lead-acid, the other a 30 kVA unit based on Li-ion).
These technologies aimed to offer fuel efficiency, lower carbon intensity and better capacity utilisation compared to conventional diesel generators which are used by DNOs during emergencies or planned power outages.
PNDC facilities include:
HV Network
- Three underground feeders for a total equivalent length of 6km
- One overhead feeder for a total equivalent length of 60km
- 11kV/400V transformers from 500kVA to 25kVA
LV Network
- Transformers ~ 50 to 315 kVA
- Mock impedances ~ 0.6 km
- Load banks ~ 600 kVA (total)
Simulation
- Hardware in the Loop Simulation
- 3-50µs simulation time-step … up to 96 3 phase busses
- Accurate frequency response up 3kHz
While the larger technology did not successfully complete testing, the smaller scale technology successfully identified and resolved issues and eventually proved resilient and capable of offering cost benefits to networks.
It is understood that a number of unity of this successful technology have now been purchased by PNDC member network.
What did PNDC do?
PNDC carried out accelerated testing of the complete system (control functionality + fuel saving + harmonics) over 24 loading cycles to prove that the system was ready for deployment by the electricity distribution network operator.
Any improvements required, in terms of grid operation standards, were shared with the clients and this joint development ensured it was ready for deployment
2) New generation Fault Passage Indicators
Fault passage indicators (FPIs) have been used for a number of years on 11KV networks as a cost effective way to indicate the passage of fault current. However, their reliability has historically been patchy.
Over the course of the last two years, following a number of strides in embedded technologies and wireless communications for FPIs, PNDC has been involved in approximately five separate FPI projects in which they impose a high volume and variety of faults onto its network to test technology capability and resilience.
What did PNDC do?
Used a complementary set of network and laboratory simulation tests to reflect realistic operating conditions for FPI technologies. This included heavy use of the PNDC high voltage fault thrower.
It conducted thorough evaluation of FPI performance under these conditions. This performance data enables improved understanding of FPI reliability and how indications should be integrated into network automation and post-fault recovery schemes.
Following testing PNDC collated findings to gain a wider picture of communications related issues for FPIs and also issued relevant findings to inform network projects under the Innovation Funding Incentive
3) Alexander Dennis Limited – Hybrid Bus
A number of collaborative partners including bus manufacturing Alexander Dennis, BAE Systems, Axeon Power and SSE came to PNDC to test the viability of the charging technology for a low emissions bus. The hybrid vehicle couples a diesel engine with and induction charged battery.
Successful testing led to a demonstration project being announced by Transport for London using and upgraded and extended range of diesel hybrid double decker busses from Alexander Dennis. This trial is due to commence spring 2016. A broader outcome for network companies however is improved understanding of the effects of harmonics from power control systems on low voltage network infrastructure.
What did PNDC do?
Installed a custom-built induction charging facility which was to evaluate; the viability of installing induction plates in standard bus bays; the reliability of GPS positioning systems to accurately park the bus over the induction charging plate; the efficiency of the charge and discharge rate of the battery; the potential impact of harmonic interruptions from the charging system on the low voltage network
4) New generation Automatic Voltage Regulator
PNCC engaged in a UK testing project for a technology from the USA which had been identified during a Low Carbon Innovation Fund initiative. Adding by adding sophisticated control parameters to standard tap changers, this technology offers a smarter solution to common network challenges around sustaining and boosting voltage on remote parts of the network.
Unlike conventional Automatic Voltage Regulator offerings, this technology operates using measure of current rather than voltage. They can also be configured in delta formation rather than in-line, resulting in cost benefits for networks.
The successful testing of this US technology has improved understanding of its potential for use in the UK. An independent review of PNDC’s project report has also identified that the findings should be used to inform training of networks’ technical and operations staff.
What did PNDC do?
The scope of the testing extended to Cooper Power Systems’ VR-32 voltage regulators under different scenarios and with different configuration of the CL-6 Series controllers
These regulators rated at 11 kV, 220 kVA were connected to PNDC’s test network in closed-delta configuration. A range of settings were tested under simulated scenarios to produce a comprehensive set of use case data
5) Soft Open Point Project
This project aimed to release capacity across the UK’s existing networks and defer the need for investment in reinforcement by synchronising and balancing across three phase connections or at points of interconnection between low voltage feeders. The capacity released through this approach should help networks to connect more sources of renewable power or low carbon technologies like electric vehicles.
The Soft Open Point (SOP) technology applies power electronics to balance the load across the points of imbalance, achieving better utilisation of capacity.
During testing at PNDC the SOP was connected at the open point of three separate low voltage feeders connected to different 11kV/415V substations on PNDC’s private network. the SOP technology was deployed on a live network as a prototype trial in late 2015.
What did PNDC do?
Carried out three phase and single phase reactive power transfer capability as well as evaluation of the SOP’s ability to provide network voltage support and fault and frequency variation protection. The SOPs responses to simulated network were monitored using calibrated power quality analysers at output terminals.
PNDC evaluated end to end capability of the SOP, specifically; monitoring, communication and control system capability
Comments
Login on register to comment
Related content

Power
The future for vegetation management
Why networks should focus on data not trees to overcome the costly challenges involved in vegetation management

Power
An unprecedented opportunity for change
Why short interruptions will matter in RIIO-ED2 and how to address them.

Power
Time for less talk and more action on decarbonisation
Core "oven-ready" solutions to decarbonising heat and transport exist today and should be implemented without delay, says WPD's future power networks expert.
Related supplier content

Power
Load patterns and lockdown: how Covid-19 is impacting electricity networks
Insights into dynamics on the low voltage network as the outbreak unfolds

Downloads
Protect electrical equipment from insulation failure
Insulation faults are a major cause leading to the eventual failure of electrical equipment. Partial discharge (PD) is a very reliable indicator of developing insulation faults. Regular PD testing allows users to detect and analyze PD activity

Heat
How E.ON. is helping the City of London become a zero emissions city
Discover Citigen. Deep in the heart of our bustling capital