£2.8m substation boosts Perth’s electricity network
Scottish and Southern Electricity Networks (SSEN) has completed a £2.8 million substation upgrade in Perth.
3rd September 2019 by Networks

The project will connect approximately 3,000 additional homes, Scotland’s newest secondary school and other amenities being constructed as part of a development on the Inveralmond Industrial Estate.
3.5km of underground cables have also been installed to increase the security of supply to surrounding properties in the area, improving the resilience of the existing electricity network currently delivering power to local homes and businesses.
John Thoms, project delivery manager at SSEN, said: “We’re delighted to complete the construction and energisation of Inveralmond Primary substation, delivering essential electricity supplies to power homes and businesses for years to come.
“Over the next decade, the Bertha Park community is set to grow substantially, and at SSEN we had to ensure the electricity network was equipped to cope with this increase in demand.”
Comments
Login on register to comment
Related content

Power
The future for vegetation management
Why networks should focus on data not trees to overcome the costly challenges involved in vegetation management

Power
An unprecedented opportunity for change
Why short interruptions will matter in RIIO-ED2 and how to address them.

Power
Time for less talk and more action on decarbonisation
Core "oven-ready" solutions to decarbonising heat and transport exist today and should be implemented without delay, says WPD's future power networks expert.
Related supplier content

Power
Load patterns and lockdown: how Covid-19 is impacting electricity networks
Insights into dynamics on the low voltage network as the outbreak unfolds

Downloads
Protect electrical equipment from insulation failure
Insulation faults are a major cause leading to the eventual failure of electrical equipment. Partial discharge (PD) is a very reliable indicator of developing insulation faults. Regular PD testing allows users to detect and analyze PD activity

Heat
How E.ON. is helping the City of London become a zero emissions city
Discover Citigen. Deep in the heart of our bustling capital