Capula hits deadline on SCS upgrade framework

The work included an upgrade at Hutton substation where Capula’s approach cut the traditional nine months it takes to do a full replacement to just eight weeks, with just one primary circuit outage over the usual multiple outages.

Capula hits deadline on SCS upgrade framework Read More »